Almond Grove Project

This page has been created to provide regular updates to the residents about the progress of the Almond Grove Street Rehabilitation Project. The first phase of the project is currently under construction and includes the rehabilitation of
Broadway (between W. Main Street and S. Santa Cruz Avenue), and Bachman Avenue (between Glen Ridge Avenue and N. Santa Cruz Avenue).
The second phase of the project is currently under design and includes the rehabilitation of remaining 8 streets within the Almond Grove Historic District.
We encourage interested parties to subscribe to the “NOTIFY ME” service located on the left hand side of this page in order to be notified immediately each time the project page is updated.

Construction Update on Almond Grove Phase I – Broadway and Bachman Avenue

    
Update posted 12/14/16 –
The Almond Grove Phase I Project is now substantially completed with both Broadway and Bachman Avenue paved and re-opened to traffic.  During the next few weeks, depending on the weather, construction crews will be finishing up minor concrete repairs and installing monument boxes along the centerline of both streets.  The final pavement markings will also be installed and a final project clean up completed.  These operations will require localized traffic control, but we do not anticipate any further road closures or detours.  
 
This will be the last weekly update for the Almond Grove Phase I project and the project team would like to thank all of the residents, businesses, and the surrounding community for your patience during this project.  

Update posted 12/12/16 –
Bachman Avenue
The following intersections will remain CLOSED to allow construction crews to complete work in these areas:  
  • Massol Avenue @ Bachman Avenue
  • Glen Ridge @ Bachman Avenue
  • Alleyway between Tait and Massol @ Bachman Avenue
  • Tait Avenue @ Bachman Avenue (limited to southbound travel only – northbound detoured to Wilder Avenue)
Additionally, the completion of the asphalt conform paving at the intersection of N. Santa Cruz Avenue and Bachman Avenue will require intermittent lane closures as the paving is completed.

It is anticipated that the current roadway and intersection closures and detours will be removed later this week, but until then, please continue to follow the designated detours and obey the closure signs.  Although it may be extremely tempting to drive on the new roadway pavement, please do not drive on the new pavement until the project team has removed the barricades and caution tape.  

Update posted 12/7/16 –
Bachman Avenue
Today construction crews placed the last section of concrete roadway on Bachman Avenue between Tait Avenue and Glen Ridge Avenue.  Thank you for your patience while this work was being completed.   

Crews will be working into the evening hours to finish the concrete and protect it from the upcoming rains.  Once again, the sawcutting operation is anticipated to take place late this evening and into the very early morning hours on Thursday.  Due to the colder temperatures and anticipated rain, it is likely that the concrete will take longer to cure and sawcutting may continue into the daytime tomorrow.  We apologize for any inconvenience and disruption caused by the noise and lights required for this operation, but please remember this is a critical element of the concrete roadway, the timing of which is dependent on many variables beyond our control.

The following intersections are to remain CLOSED over the weekend, please obey all road closure and detour signs:

  • Massol Avenue @ Bachman Avenue
  • Glen Ridge @ Bachman Avenue
  • Alleyway between Tait and Massol @ Bachman Avenue
  • Tait Avenue @ Bachman Avenue (limited to southbound travel only – northbound detoured to Wilder Avenue)
The newly placed roadway sections and intersections will remain closed throughout the weekend.  Although it may be extremely tempting to walk or drive on the new roadway pavement, please stay off of the new pavement until the project team has determined the pavement is able to accommodate traffic and has removed the barricades and caution tape. For pedestrian access, please use the sidewalks to navigate around the construction area.  

****************************************************************

TWO WEEK LOOK AHEAD

  

 

12/16/16-1/6/17

 
Broadway
  • Completion of pavement markings, red curbs (weather dependent)
  • Minor concrete repairs
  • Drainage inlet installation
  • Centerline monument installations
  • Final project clean-up
Bachman Avenue
  • Completion of pavement markings, red curbs (weather dependent)
  • Minor concrete repairs
  • Centerline monument installations
  • Final project clean-up

Update posted 12/6/16 –
Bachman Avenue
Construction crews are prepared to place the last section of roadway on Bachman Avenue between Tait Avenue and Glen Ridge Avenue tomorrow, Wednesday, December 7th.  In an effort to place the concrete before the rains predicted for tomorrow evening, construction crews will begin working at 7a.m.  To expedite the construction, Bachman Avenue between Tait and Belmont Avenues will be closed to through traffic for most of the day on Wednesday, December 7th, including the intersections of Massol/Bachman and Glen Ridge/Bachman.   Local access to properties on the north side of Bachman Avenue between Tait and Glen Ridge will be maintained, however there may be 10 – 15 minute delays while the concrete trucks place their loads.  Please consider using alternate routes and/or allow additional time for accessing properties in the area.  Once the new roadway section has been placed, westbound Bachman will be reopened to traffic, however the intersections of Massol/Bachman and Glen Ridge/Bachman Avenues will remain closed over the weekend and until the concrete roadway has cured sufficiently to be opened back up to traffic. 
 
Sawcutting of the newly placed roadway section is anticipated to take place in the late evening hours of Wednesday night and into the early morning hours on Thursday, depending on the cure time of the concrete.  Again we apologize in advance for the disruption that will be created by the noise and lights of this operation.


Update posted 12/1/16 –
Bachman Avenue
The new concrete roadway on the south side of Bachman Avenue between N. Santa Cruz Avenue and Tait Avenue was poured today, including the southwest quadrant of the Tait/Bachman intersection.  Please be advised that only northbound traffic on Tait across Bachman will be allowed.  Traffic wishing to travel southbound across Bachman Avenue will be detoured to cross at Massol Avenue. 

Working hours have been extended beyond 5:00 pm tonight in order to allow the contractor to finish the roadway as the colder temperatures have slowed the curing time for the concrete.  As with previous sections, it is anticipated that the required sawcutting of the new pavement will need to occur during the late evening hours tonight and into the very early morning hours on Friday.  We apologize in advance for the disruption and inconvenience that the noise and lights from this operation will cause, however please remember the saw cuts are of major importance to the performance of the concrete roadway and must be completed at very specific times which are determined by factors beyond our control.       

The newly placed roadway sections will remain closed during this weekend’s Holiday parade and this closure has been coordinated with the parade organizers.   Although it may be extremely tempting to walk or drive on the new roadway pavement, please stay off of the new pavement until the project team has determined the pavement is able to accommodate traffic and has removed the barricades and caution tape. For pedestrian access, please use the sidewalks to navigate around the construction area.  

Residents and businesses along this newly poured section of roadway will continue to be without driveway access until the roadway has cured sufficiently to accommodate vehicular traffic.  If you live on other sections of Bachman Avenue and have the ability to park in your driveway, we encourage you to do so and make the limited street parking available to those residents who are without driveway access. All efforts will be made to re-open driveway access as quickly as possible, and will depend on the cure time of the concrete as placed.  

The following intersections are to remain CLOSED, please obey all road closure and detour signs:

  • Wilder Avenue @Bachman Avenue
  • Victory Lane @ Bachman Avenue
  • Alleyway between Wilder and Tait @ Bachman Avenue
  • Tait Avenue @ Bachman Avenue (limited access – please use Massol Avenue)
Update posted 11/22/16 –
Bachman Avenue
The removal and replacement of the concrete roadway pavement between N. Santa Cruz Avenue through the Tait Avenue intersection is currently scheduled to begin Monday, November 28th , depending on a clear weather forecast for the week.   Should the weather forecast change, the construction schedule will be modified accordingly.  Please take note of the following changes in traffic patterns necessary to complete the street reconstruction.
 
Beginning Monday, November 28th  the following intersections are scheduled to be CLOSED:
  • Tait Avenue @ Bachman Avenue
  • Wilder Avenue @Bachman Avenue
  • Victory Lane @ Bachman Avenue
  • Alleyway between Wilder and Tait @ Bachman Avenue
 The Massol/Bachman Avenue intersection is scheduled to be opened to traffic prior to the closure of these intersections.  Traffic wishing to cross Bachman Avenue at any of these cross streets will be detoured to Massol Avenue.  
 
Residents on Bachman Avenue will continue to receive garbage and recycling collection services on Thursdays (including Thanksgiving Day).  Please continue to place containers at the curb, or in the driveway approach if the roadway is under construction.  The contractor may move the containers to an alternate location to be emptied, but will return them to their original location following the collection service. 

  

 (Update posted on 4/29/16) Resident and business owner pre-construction meetings were held on April 25th and April 26th to discuss the upcoming construction with the residents and business owners on Broadway, Clifton Avenue, and Bachman Avenue who will be directly impacted the by construction work.  The agenda and presentation slides for those meetings can be viewed by clicking on the links below.
A list of Frequently Asked Questions resulting from the meeting and regarding the construction project can be found in the following link:
Phase I Construction FAQs

 If you have questions regarding the construction of this project, please contact Michelle Quinney, Special Projects Manager, at (408) 827-3552 or MQuinney@LosGatosCA.gov
 
Please click on the following links for additional information regarding the Broadway and Bachman Avenue construction project:
• Resident/Business Owner meeting agenda – April 24th and 25th, 2016
• Resident/Business Owner presentation slides – April 24th and 25th, 2016
• Resident/Business Owner meeting – door hangers – April 11, 2016
• Resident/Business Owner meeting letter – April 11, 2016
• Town Council award of contract – February 16, 2016

Almond Grove Project Phase I Design Information


Please click on the following links for information related to the design of the Almond Grove Project.

If you have questions regarding the design of the Almond Grove Project, please contact Lisa Petersen, Town Engineer, at (408) 399-5773 or LPetersen@LosGatosCA.gov

Almond Grove Phase I - Plans, Specifications & RFP
Please note that the Plans and Specifications shown below are for information only and should not be used for bidding purposes.

Project #13-31 Almond Grove Street Reconstruction Phase I (Asphalt) 

Project #13-31 Almond Grove Street Reconstruction Phase I (Concrete) 

Ordinances Related to Almond Grove Historic District