Almond Grove Project

This page has been created to provide regular updates to the residents about the progress of the Almond Grove Street Rehabilitation Project. The first phase of the project is currently under construction and includes the rehabilitation of
Broadway (between W. Main Street and S. Santa Cruz Avenue), and Bachman Avenue (between Glen Ridge Avenue and N. Santa Cruz Avenue).
The second phase of the project is currently under design and includes the rehabilitation of remaining 8 streets within the Almond Grove Historic District.
We encourage interested parties to subscribe to the “NOTIFY ME” service located on the left hand side of this page in order to be notified immediately each time the project page is updated.

Construction Update on Almond Grove Phase I – Broadway and Bachman Avenue

    
Update posted 12/1/16 –
Bachman Avenue

The new concrete roadway on the south side of Bachman Avenue between N. Santa Cruz Avenue and Tait Avenue has been placed, including the southwest quadrant of the Tait/Bachman intersection.  
The newly placed roadway sections will remain closed during this weekend’s Holiday parade, including a portion of the Tait/Bachman intersection, and this closure has been coordinated with the parade organizers.   Although it may be extremely tempting to walk or drive on the new roadway pavement, please stay off of the new pavement until the project team has determined the pavement is able to accommodate traffic and has removed the barricades and caution tape. For pedestrian access, please use the sidewalks to navigate around the construction area.  

The following intersections are to remain CLOSED over the weekend, please obey all road closure and detour signs:
  • Wilder Avenue @Bachman Avenue
  • Victory Lane @ Bachman Avenue
  • Alleyway between Wilder and Tait @ Bachman Avenue
  • Tait Avenue @ Bachman Avenue (limited access – please use Massol Avenue)
Once the recently placed pavement has cured and is able to accommodate traffic, these intersections will be re-opened and the following intersections will be closed.  It is highly likely that this will take place on Monday, December 5th:
  • Massol Avenue @ Bachman Avenue
  • Glen Ridge @ Bachman Avenue
  • Alleyway between Tait and Massol @ Bachman Aveneu
  • Tait Avenue @ Bachman Avenue (limited to southbound travel only – northbound detoured to Wilder Avenue)

Broadway 
New permit parking signs and posts are scheduled to be installed next week.  Although the signs and posts are new, they will be replaced in the original location.    Once these signs are installed, the temporary 24 hour permit parking only restriction will be removed and Broadway will revert to the original permit parking conditions.
****************************************************************

TWO WEEK LOOK AHEAD

  

 

12/5/16-12/18/16

 
Broadway
  • Potential installation of pavement markings, red curbs (weather dependent)
  • Installation of new signposts and signs, and removal of 24 hour permit parking only restrictions (postponed from 11/30/16 to 12/9/16)
  • Potential minor concrete repairs
Bachman Avenue
  • Complete removal and replacement of the concrete roadway – south half between Tait Avenue and Glen Ridge Avenue (depending on weather)
  • Closure of Massol/Bachman and Glen Ridge/Bachman intersections
  • Raising of utilities in new roadway area
  • Potential paving of asphalt conforms at side streets
  • Potential installation of pavement markings, red curbs, street signs (weather dependent)
  • Potential minor concrete repairs


Update posted 12/1/16 –
Bachman Avenue
The new concrete roadway on the south side of Bachman Avenue between N. Santa Cruz Avenue and Tait Avenue was poured today, including the southwest quadrant of the Tait/Bachman intersection.  Please be advised that only northbound traffic on Tait across Bachman will be allowed.  Traffic wishing to travel southbound across Bachman Avenue will be detoured to cross at Massol Avenue. 

Working hours have been extended beyond 5:00 pm tonight in order to allow the contractor to finish the roadway as the colder temperatures have slowed the curing time for the concrete.  As with previous sections, it is anticipated that the required sawcutting of the new pavement will need to occur during the late evening hours tonight and into the very early morning hours on Friday.  We apologize in advance for the disruption and inconvenience that the noise and lights from this operation will cause, however please remember the saw cuts are of major importance to the performance of the concrete roadway and must be completed at very specific times which are determined by factors beyond our control.       

The newly placed roadway sections will remain closed during this weekend’s Holiday parade and this closure has been coordinated with the parade organizers.   Although it may be extremely tempting to walk or drive on the new roadway pavement, please stay off of the new pavement until the project team has determined the pavement is able to accommodate traffic and has removed the barricades and caution tape. For pedestrian access, please use the sidewalks to navigate around the construction area.  

Residents and businesses along this newly poured section of roadway will continue to be without driveway access until the roadway has cured sufficiently to accommodate vehicular traffic.  If you live on other sections of Bachman Avenue and have the ability to park in your driveway, we encourage you to do so and make the limited street parking available to those residents who are without driveway access. All efforts will be made to re-open driveway access as quickly as possible, and will depend on the cure time of the concrete as placed.  

The following intersections are to remain CLOSED, please obey all road closure and detour signs:

  • Wilder Avenue @Bachman Avenue
  • Victory Lane @ Bachman Avenue
  • Alleyway between Wilder and Tait @ Bachman Avenue
  • Tait Avenue @ Bachman Avenue (limited access – please use Massol Avenue)
Update posted 11/22/16 –
Bachman Avenue
The removal and replacement of the concrete roadway pavement between N. Santa Cruz Avenue through the Tait Avenue intersection is currently scheduled to begin Monday, November 28th , depending on a clear weather forecast for the week.   Should the weather forecast change, the construction schedule will be modified accordingly.  Please take note of the following changes in traffic patterns necessary to complete the street reconstruction.
 
Beginning Monday, November 28th  the following intersections are scheduled to be CLOSED:

  • Tait Avenue @ Bachman Avenue
  • Wilder Avenue @Bachman Avenue
  • Victory Lane @ Bachman Avenue
  • Alleyway between Wilder and Tait @ Bachman Avenue
 The Massol/Bachman Avenue intersection is scheduled to be opened to traffic prior to the closure of these intersections.  Traffic wishing to cross Bachman Avenue at any of these cross streets will be detoured to Massol Avenue.  
 
Residents on Bachman Avenue will continue to receive garbage and recycling collection services on Thursdays (including Thanksgiving Day).  Please continue to place containers at the curb, or in the driveway approach if the roadway is under construction.  The contractor may move the containers to an alternate location to be emptied, but will return them to their original location following the collection service.

Update posted 11/17/16 –
Bachman Avenue-
Construction crews are working to switch traffic onto the new concrete roadway between N. Santa Cruz Avenue and Tait Avenue.  The one lane of westbound traffic in this segment will soon be traveling on the north half of Bachman Avenue.  In this area, on street parking will also be shifted to the northern half of the street only.  The southern half of Bachman Avenue between N. Santa Cruz and Tait Avenue will be closed to prepare for the upcoming roadway removal and replacement.  Access to and from properties on the south side of Bachman Avenue will be maintained until the roadway removal begins.  

Due to rain in the forecast, the actual start of the roadway removal and replacement on the south side of Bachman Avenue is on hold until after the Thanksgiving holiday.  Should the weather forecast change, the construction schedule will be modified accordingly.   

Please be aware of the change in traffic patterns on Bachman Avenue and obey all traffic control signs. 

The section of roadway recently placed between Tait Avenue and Glen Ridge Avenue is still in the curing process and is not ready to accept vehicular traffic.  Although it may be extremely tempting to drive on this new roadway pavement, please stay off of the new pavement until the project team has determined the pavement is able to accommodate vehicular traffic and has removed the barricades and caution tape. For pedestrian access, please use the sidewalks to navigate around and through the construction area.


Update posted 11/16/16 –
New concrete pavement is being placed today on the north half of Bachman Avenue between Tait Avenue and Glen Ridge Avenue.  Please be advised that the saw cutting of the new concrete roadway placed today will most likely occur during the late evening hours tonight (Wednesday) and into the very early morning hours on Thursday.  We apologize in advance for the disruption and inconvenience that the noise and lights from this operation will cause, however please understand that the saw cuts are of major importance to the performance of the concrete roadway and must be completed at very specific times which are determined by factors beyond our control. 

Although it may be extremely tempting to drive on the new roadway pavement, please stay off of the new pavement until the project team has determined the pavement is able to accommodate vehicular traffic and has removed the barricades and caution tape. For pedestrian access, please use the sidewalks to navigate around and through the construction area.



Update posted 11/14/16 –
The intersection of Massol Avenue and Bachman Avenue will be closed this afternoon at 2:00 p.m.  The intersection of Tait Avenue and Bachman Avenue will be reopened at the same time.  Traffic wishing to travel across Bachman Avenue in the north/south directions will be detoured to Tait Avenue.  Construction crews will continue the removal of the concrete pavement and the preparation of the area on the north half of Bachman Avenue between Tait and Glen Ridge Avenues, and currently anticipate placing concrete for this segment on Wednesday of this week. 

Update posted 11/11/16 –
Bachman Avenue Paving Update –  
Vanguard crews will be working on Bachman Avenue this Saturday to prepare the next segment of Bachman Avenue for the new concrete roadway.  Work is anticipated to consist of the grading of the roadway as well as the placement of form boards between Tait Avenue and Glen Ridge Avenue.  Crews are being allowed to work over the weekend in order to take advantage of clear weather since rains are forecasted for next week.  No concrete will be placed this weekend, however, as mentioned in previous updates, the saw cutting of the concrete roadway placed today will most likely occur during the late evening hours tonight (Friday) and into the very early morning hours on Saturday. We apologize in advance for the disruption and inconvenience that the noise and lights from this operation will cause, however please remember the saw cuts are of major importance to the performance of the concrete roadway and must be completed at very specific times which are determined by factors beyond our control.      
 
If you live on the south half of Bachman Avenue and have the ability to park in your driveway, we encourage you to do so.  This will allow the limited street parking to be available to those residents on the north side of Bachman Avenue who are currently without driveway access. All efforts will be made to re-open driveway access as quickly as possible.   
 
Over the weekend it may be extremely tempting to drive on the new concrete roadway pavement, however, please stay off of the new pavement until the project team has determined the concrete has cured sufficiently and is able to accommodate vehicular traffic, and has removed the barricades and caution tape.   For pedestrian access, please use the sidewalks to navigate around and through the construction area.

Update posted 11/10/16 –
Bachman Avenue Paving Update –  
The first new concrete roadway segment on Bachman Avenue is scheduled to be poured on Friday, November 11th.  The placement of this new concrete pavement on the north half of Bachman Avenue between N. Santa Cruz and approximately 300 Bachman Avenue is scheduled to begin at 7:30 am in order to take full advantage of daylight hours.  It is extremely likely that the required sawcutting of the new pavement will need to occur during the late evening hours Friday and into the very early morning hours on Saturday. We apologize in advance for the disruption and inconvenience that the noise and lights from this operation will cause, however please remember the saw cuts are of major importance to the performance of the concrete roadway and must be completed at very specific times which are determined by factors beyond our control.     

Residents and businesses along this new section of roadway will continue to be without driveway access until the roadway has cured sufficiently to accommodate vehicular traffic.  If you live on other sections of Bachman Avenue and have the ability to park in your driveway, we encourage you to do so and make the limited street parking available to those residents who are without driveway access. All efforts will be made to re-open driveway access as quickly as possible, and will depend on the cure time of the concrete as placed.   

Over the weekend it may be extremely tempting to drive on the new roadway pavement, however, please stay off of the new pavement until the project team has determined the pavement is able to accommodate vehicular traffic and has removed the barricades and caution tape. For pedestrian access, please use the sidewalks to navigate around and through the construction area.

Residents are also reminded to please put out all collection and recycling carts on the regularly scheduled collection day. The contractor is coordinating the collection services with WVCR  and may need to move your carts to a location for collection, but will return the carts once they have been emptied by WVCR.  
 (Update posted on 4/29/16) Resident and business owner pre-construction meetings were held on April 25th and April 26th to discuss the upcoming construction with the residents and business owners on Broadway, Clifton Avenue, and Bachman Avenue who will be directly impacted the by construction work.  The agenda and presentation slides for those meetings can be viewed by clicking on the links below.
A list of Frequently Asked Questions resulting from the meeting and regarding the construction project can be found in the following link:
Phase I Construction FAQs

 If you have questions regarding the construction of this project, please contact Michelle Quinney, Special Projects Manager, at (408) 827-3552 or MQuinney@LosGatosCA.gov
 
Please click on the following links for additional information regarding the Broadway and Bachman Avenue construction project:
• Resident/Business Owner meeting agenda – April 24th and 25th, 2016
• Resident/Business Owner presentation slides – April 24th and 25th, 2016
• Resident/Business Owner meeting – door hangers – April 11, 2016
• Resident/Business Owner meeting letter – April 11, 2016
• Town Council award of contract – February 16, 2016

Almond Grove Project Phase I Design Information


Please click on the following links for information related to the design of the Almond Grove Project.

If you have questions regarding the design of the Almond Grove Project, please contact Lisa Petersen, Town Engineer, at (408) 399-5773 or LPetersen@LosGatosCA.gov

Almond Grove Phase I - Plans, Specifications & RFP
Please note that the Plans and Specifications shown below are for information only and should not be used for bidding purposes.

Project #13-31 Almond Grove Street Reconstruction Phase I (Asphalt) 

Project #13-31 Almond Grove Street Reconstruction Phase I (Concrete) 

Ordinances Related to Almond Grove Historic District