- Home
- Living in Los Gatos
- Town Departments and Services
- Parks and Public Works
- Capital Improvement Program
- Connect Los Gatos
- Shannon Pedestrian and Bikeway Improvement Project
Shannon Pedestrian and Bikeway Improvement Project
Project Background
Shannon Road serves as a major pedestrian corridor for students attending three nearby schools, with the most heavily trafficked portion of this corridor spanning from Los Gatos Boulevard to Cherry Blossom Lane. Much of this corridor is missing sidewalk. The Los Gatos – Monte Sereno Bicycle and Pedestrian Master Plan (BPMP) includes a Town-wide priority to add missing sidewalks along school walking routes such as this, and identifies both bicyclists and pedestrians improvements along the Shannon Road corridor. Pursuant to these goals, the Town applied for, and received, a $940,100 Vehicle Emissions Reductions Based at Schools (VERBS) federal grant from the Santa Clara Valley Transportation Authority (VTA) for the improvements recommended in the Master Plan. In addition, the Town applied for and received a Transportation Fund for Clean Air Grant of $174,250 for this project.
The current plan for the project is to construct sidewalks and buffered Class II bike lanes on both sides of Shannon Road between Los Gatos Blvd. and Cherry Blossom Lane. The project would involve installation of a new curb, gutter, sidewalk, buffered Class II bike lanes, and ADA curb ramps on Shannon Road within the project limits. The work scope may also include improvements to the storm drainage system.
The goal of the project is to improve a public street that serves a broad community, making the location safer for all users while retaining the functionality and aesthetics important to the Town.
Project Updates
Project Update September 4, 2025
The Shannon Road Pedestrian and Bicycle Improvement project is officially completed. It is operational and open to the public for use.
Project Update June 28, 2025
The Shannon Road Pedestrian and Bicycle Improvement project is entering the final phase. Upcoming work is set to begin Monday, June 23. This phase will include roadway excavation, asphalt overlay, and new striping. Striping will feature a new Class II buffered bike lanes. Construction will take place between 8 AM to 5 PM, Monday through Friday.
Traffic lane closures will be in effect, and detours will be provided for vehicles, bicyclists, and residents. Residents should expect noise, dust, odors, and traffic delays. “No Parking” Signs will be posted 72 hours in advance of starting construction.
At the conclusion of the work, roadway will have flatter slopes and a smoother surface. This will improve the safety and ride quality for all users.”
Project Update April 7, 2025
The Shannon Pedestrian and Bicycle Improvement project continues to progress. Concrete sidewalks and ADA-compliant ramps have been installed along both the north and south sides of Shannon Road. The contractor is currently awaiting completion of utility work by San Jose Water before proceeding with the installation of the new storm drain line. Further updates will be provided as the project advances.
Project Update February 5, 2025
The Shannon Pedestrian and Bicycle Improvement project is continuing to progress. The concrete sidewalks along the north side of Shannon road are completed. Contractor is currently demolishing and installing new concrete sidewalk, curb and gutter on the south side of Shannon road.
Contractor is also installing a new storm drain line along Shannon road. The storm drain line has been delayed due to a utility conflict with a water line and sewer line. We have also run into other utility issues with PG&E and Frontier Communications. We are awaiting final design resolution.
Project Update September 9, 2024
The contractor has encountered an unforeseen two week delay. As a result, the contractor will mobilize onsite in mid-September. In the coming week, contractor will begin laying out back of walk markings and setting up traffic control. Demolition for Phase 1 (north side of Shannon Road) will follow subsequently.
Project Update August 30, 2024
Construction on the Shannon Road Pedestrian and Bike Improvement Project will begin on September 3, 2024. Phase 1 of the project will take place along the north side of Shannon Road between Cherry Blossom Lane and Los Gatos Boulevard. In early September, project contractor Sposeto Engineering, will set up traffic control and begin demolition. This will include removal of landscaping, trees and other assets in the public right of way to accommodate project improvements. This will be followed by the set-up of forms and pour of concrete. Phase 1 is expected to be completed in mid-October.
PGE will also be out on-site concurrently during relocating their utility poles in the project reach. Joint pole relocation is a critical work activity that will enable Sposeto Engineering to proceed with their work without delays.
After phase 1 is complete, work will begin immediately on Phase 2. Phase 2 will perform similar work on the south side of Shannon Road. During the work, traffic control will be in place to protect pedestrian and cyclist safety.
Project Update August 19, 2024
Sposeto Engineering is planning to perform construction staking on Wednesday, August 21, 2024. You may notice survey crews in your area, and along your frontage during this time. This task is being performed in preparation for the overall project.
We are still in the process of finalizing a full project schedule. The Town is working closely with Sposeto Engineering and utility agencies to establish a critical path for the project. We will keep you updated as the project progresses.
Project Update July 30,2024
We are pleased to announce that the construction contract for Shannon Road Bicycle and Pedestrian Project was awarded to Sposeto Engineering on June 18, 2024. The Town is actively working with Sposeto Engineering and utility agencies to establish a construction schedule. We will provide additional information as soon as it becomes available.
- Advertise Project for construction May 3
- Open Bids May 29
- Town Council Award of Contract June 18
- Notice to Proceed Issued TBD
- Anticipated Construction Start TBD
- Anticipated Construction End TBD
The final construction drawings can be found in the link below.
Project Update April 22,2024
The final plans have been completed for the Shannon Road Bicycle and Pedestrian Project. Thanks to the community who provided input during the outreach efforts over the past several months. Valuable feedback received from those community outreach efforts drove many of the project changes that will ultimately result in a better project for the community. Below is the updated project schedule:
- Advertise Project for construction May 3
- Open Bids May 29
- Town Council Award of Contract June 18
- Notice to Proceed Issued TBD
- Anticipated Construction Start TBD
- Anticipated Construction End End of Calendar Year
The final construction drawings can be found in the link below.
Project Update March 6, 2024
The Shannon Road Bicycle and Pedestrian Project continues to progress. Following the neighborhood outreach and Town Council meetings in June 2023, the design team went back to the drawing board, updating the plans consistent with Council direction. The finishing touches are currently being put on the construction specifications.
The following is the anticipated project schedule:
- Advertise Project for Construction 4/19
- Open Bids 5/15
- Town Council Award of Contract 6/4
- Notice to Proceed Issued 6/24
- Anticipated Construction Start 7/8
- Anticipated Construction End 12/31
Project Update November 27, 2023
Parks and Public Works has finalized the project plans incorporating feedback received from the recent community meeting resulting in additional planter strips and trees along the corridor. The project has received its right-of-way certification from Caltrans and expects to bid early next year with construction to start in the spring of 2024.
Project Update June 5, 2023
Parks and Public Works hosted a community meeting on Thursday, June 1st, to present alternative concept plans and listen to community feedback on potential changes to the design. The link to the presentation can be found under Community Meetings section above. Following two design options were shared with the stakeholders:
Project Update May 2, 2023
Staff presented construction plans to Town Council on April 18, 2023. Due to concerns raised about the project, Council directed staff to modify the plans to replace the proposed parking with trees and vegetation, add trees where possible, reduce the asphalt buffers shown on the plans and hold a community meeting to discuss the changes with local residents. At this time staff is considering revisions to the design to fulfill the council direction. A community meeting should be scheduled for early June 2023.
Project Update 3-23-2023
Staff is scheduled on April 18, 2023 to update Town Council on the project’s progress and seek authorization to bid the construction contract.
NOTE: Town Council did not authorize the project for bidding on 4/18/2023 and the plans identified below are in the process of being revised.
Project Update 2-24-2022
Staff update to the Town Council for the project has been rescheduled to March 1.
Revisions have been made to the 65% Design plans from feedback and comments received at the Fourth Community Meeting on January 15. Planter strips have been lengthened (where possible) for more green space where on-street parking would be located. The changes can be viewed here:
- Revised 65% Design Plan Layout (updated 2/25/2022)
Project Update 2-1-2022
On January 15, the fourth community meeting was held in-person on Shannon Road to present the 65% design plans, discuss upcoming project schedule, gather feedback, and walk the site with individual residents to review project impacts. The meeting was advertised through door hangers, social media outlets, Town website Notify Me updates, and meeting notice signs placed along Shannon Road. Approximately 36 community members attended the meeting.
At the meeting, the Shannon Road residents commented again about making the sidewalk and bikeway improvements as narrow as possible and incorporating more planting space to keep the rural feel of the neighborhood. Staff informed the attendees that the pedestrian and bikeway elements were already narrowed to incorporate additional on-street parking on the south side of Shannon Road and the two-foot planter strips between the property line and sidewalk. However, staff would further investigate ways to incorporate more planting space if possible.
For next steps, staff is planning to provide a project update to Council on February 15 and complete 95% and 100% construction documents by the summer. Staff also mentioned that the earliest anticipated construction start on Shannon Road would be fall 2022, and that the project team will continue to work with individual residents along Shannon Road while moving forward with the final design.
Project Update 1-6-22 - Fourth Community Meeting
On Saturday, January 15, 2022 at 10 am, a fourth community meeting is scheduled to provide design updates to the Shannon Road Residents. This will be an in-person meeting and will be held on site at the driveway of 16639 Shannon Road. Anyone interested in the project is welcome to attend.
Please click on the link below to view the design plan updates to be presented at the meeting:
Project Update 12-17-21
As design consultant moves towards the 65% design, the Town staff would like to and need to engage with individual property owners “on site”. This will be the point where items such as driveway locations, transitions from the project improvements to the private property, etc. can be discussed. Town staff will be reaching out individually to schedule these. The Town is experienced in working on projects alongside private property to ensure that the private property is not damaged or is replaced in kind, and is committed to continuing this success.
Community member input is extremely important in the decision making process. Additional community meeting and presentation to the Complete Streets and Transportation Commission will be held to obtain feedback before the item goes to the Town Council for their consideration. The plan is to bring the 65% design to the Town Council in February and continue design towards a project that is ready for approval to bid in April. Both of these will be public meetings where residents are encouraged to participate.
Project Update 11-17-21 - Third Community Meeting
The Town of Los Gatos, Parks and Public Works Department, hosted an on-line community meeting for the Shannon Road Pedestrian and Bikeway Improvement Project, on November 17, 2021. The project team solicited valuable community input regarding the current project design. Please click on the link below to access the PowerPoint presentation that was shared.
Online Survey and November 17 Community Meeting Announcement
On October 19, 2021, the Town Council approved Design Concept 3 (buffered bike lanes) without the green bollards for the Shannon Road Pedestrian and Bikeway Improvement Project. View the Design Concept 3 here:
Before proceeding with the final design, there are few adjustments that can be made to the current design concept. An online survey is being conducted by the Town to gather feedback from the Shannon Road residents regarding the importance/priorities of certain design elements.
The online survey is only for the residents residing/abutting Shannon Road between Los Gatos Boulevard and Cherry Blossom Lane.
The online survey is only for the residents residing/abutting Shannon Road between Los Gatos Boulevard and Cherry Blossom Lane.
Project Update 10-13-21
Town staff is recommending that the Town Council approves Design Concept 3. The Council will consider the recommendations at its meeting on 10/19. The meeting Agenda and Zoom webinar information will be posted on the link below. Community members are strongly encouraged to attend the meeting and provide comments.
At the Complete Street Transportation Commission (CSTC) on 10/14, staff shared the three design concepts and received feedback. The CSTC 10/14 meeting agenda and information are posted on the link below:
https://www.losgatosca.gov/AgendaCenter/Complete-Streets-and-Transportation-Comm-25
The project is recommended for a Transportation Fund for Clean Air (TFCA) grant for $174,250, pending final approval.
Community Meetings
- First Community Meeting Presentation - Aug. 26, 2021
- Second Community Meeting Presentation - Sept. 29, 2021
- Third Community Meeting Presentation - Nov. 17, 2021
- Fourth Community Meeting - Jan. 15, 2022 (on-site)
- Fifth Community Meeting - June 1, 2023
- One-on-One meetings with community members to discuss design and property impacts - December 2023
Town Council Meetings
- Approval of the Concept Design - Oct. 19, 2021
- 65% Design Project Update - Mar. 1, 2022
Conceptual Designs
- Design Concept #1 Cross Section View
- Design Concept #1 Plan View
- Design Concept #2 Cross Section View
- Design Concept #2 Plan View
- Design Concept #3 Cross Section View
- Design Concept #3 Plan View
On October 19, 2021, the Town Council approved Design Concept 3 (buffered bike lanes) without the green bollards for the Shannon Road Pedestrian and Bikeway Improvement Project.
Before proceeding with the final design, there are few adjustments that can be made to the current design concept. An online survey was conducted by the Town for the residents residing/abutting Shannon Road between Los Gatos Boulevard and Cherry Blossom Lane to gather their feedback regarding the importance/priorities of certain design elements.